SkyRidge Medical Center



Owner: SkyRidge Medical Center

Location: Cleveland, Tennessee

Size: 109,113 sq ft

Cost: $28,627,542

Completion Date: April 2009

Architect: Thomas Miller and Partners


Description: Cleveland, Tennessee was the location of a 109,113 SF addition and renovation that Robins & Morton completed at SkyRidge Medical Center. The 14-month long project, with construction costs totaling $28.6 million, finished on schedule and under budget. It included a 43-bed Emergency Department, 10-bed ICU unit, eight surgical suites with a day-surgery area, and 31 private rooms in a medical surgical unit. Robins & Morton overcame challenges such as matching the EIFS on the exterior skin to the existing building that was 10 years old and weathered, making five connection points from the addition to the existing building and adding a loading dock, helipad and two parking lots in the final two months of the project while still maintaining the original completion date.